Name & Address of Client Worksite Address Architects Consultants Project Managers Type of Installation Period of Execution Value of Work in LAKHS (INR)
AMAZON DEVELOPMENT CENTER INDIA PVT. LTD., AMAZON DEVELOPMENT CENTER INDIA PVT. LTD., C.R.NARAYANA RAO LLP ELECTRON CONSULTANTS JONES LANG LASALLE Interior Fit-out Electrical Works comprising  LT Panels, LT Cables  & End Terminations, Cable Trays,   Conduits / Point Wiring, MCB DB’s, Isolators & RCBOs, Raceways & Junction Boxes,  Dimming Control System & sensors, Light Fixtures,  Earthing etc.
1st and 2nd Floor, Adot IT Park, Behind In-orbit Mall, Pune-Nagar Road, Pune 1st and 2nd Floor, Ador IT Park, Behind In-orbit Mall, Pune-Nagar Road, Pune-411 014
50,000 Sq.Ft. Area
No.10,  Karpagambal Nagar, P.B. No. 624, Mylapore, Chennai-600 004, Tamilnadu Bangalore Level 6, Amar Avinath Corporate Plaza, 11, Bund Garden Road,
Pune-411 001
MAY’ 2015
TO
AUGUST’ 2015
200.00

 

AMAZON DEVELOPMENT CENTER INDIA PVT. LTD., AMAZON DEVELOPMENT CENTER INDIA PVT. LTD., C.R.NARAYANA RAO LLP ELECTRON CONSULTANTS JONES LANG LASALLE Interior Fit-out Electrical Works comprising  LT Panels, LT Cables  & End Terminations, Cable Trays,   Conduits / Point Wiring, MCB DB’s, Isolators & RCBOs, Raceways & Junction Boxes,  Dimming Control System & sensors, Light Fixtures,  Earthing etc.
1st and 2nd Floor, Adot IT Park, Behind In-orbit Mall, Pune-Nagar Road, Pune 1st and 2nd Floor, Ador IT Park, Behind In-orbit Mall, Pune-Nagar Road, Pune-411 014
PHASE-1
30,000 Sq.Ft. Area
No.10,  Karpagambal Nagar, P.B. No. 624, Mylapore, Chennai-600 004, Tamilnadu Bangalore Level 6, Amar Avinath Corporate Plaza, 11, Bund Garden Road,
Pune-411 001
MAY’ 2015
TO
AUGUST’ 2015
174.00

 

AMAZON DEVELOPMENT CENTRE INDIA PVT. LTD., AMAZON DEVELOPMENT CENTRE INDIA PVT. LTD., C.R.N. ARCHITECTS ELECTRON CONSULTANTS JONES LANG LASALLE Electrical Works comprising  LT Swtichboards, LT Cables & End Terminations, Conduiting / Submains / Point Wiring, MCB DBs,  Cable Trays, Raceways, Junction Boxes, Swtiches & Sockets, Light Fixtures, Earthing etc.
Divyasree Building, 3rd Floor,
Plot No.6, Hi-tech City, Sy.No.64(Part),  Madhapur Village, Serilingampalli Mandal,
Hyderabad-560 081.
Phase-2 (1st Floor Retrofit, 2nd Floor & 3rd Floor), Trion IT Park,  Hissa Nos.9+10+11+12B at 7 Ahmednagar Road, Village Vadgaon Sheri, Pune-411 014

85,000 Sq.Ft. Area

CHENNAI Bangalore Pune FEBRUARY’ 2016
TO
MAY’  2016
104.00

 

AMAZON DEVELOPMENT CENTRE INDIA PVT. LTD., AMAZON DEVELOPMENT CENTRE INDIA PVT. LTD., C.R.N. ARCHITECTS ELECTRON CONSULTANTS JONES LANG LASALLE Electrical Works comprising  LT Swtichboards, LT Cables & End Terminations, Conduiting / Submains / Point Wiring, MCB DBs,  Cable Trays, Raceways, Junction Boxes, Swtiches & Sockets, Light Fixtures, Earthing etc.
Divyasree Building, 3rd Floor,
Plot No.6, Hi-tech City, Sy.No.64(Part),  Madhapur Village, Serilingampalli Mandal,
Hyderabad-560 081.
Phase-3
Trion IT Park, Sy.No.35, Hissa Nos.9+10+11+12B at 7 Ahmednagar Road, Village Vadgaon Sheri, Pune-411 014
30,000 Sq.Ft. Area
CHENNAI Bangalore Pune APRIL’ 2016
TO
JUNE’  2016
102.00

 

AMAZON DEVELOPMENT CENTRE INDIA PVT. LTD., AMAZON DEVELOPMENT CENTRE INDIA PVT. LTD., C.R.N. ARCHITECTS ELECTRON CONSULTANTS JONES LANG LASALLE Electrical Works comprising  LT Swtichboards, LT Cables & End Terminations, Conduiting / Submains / Point Wiring, MCB DBs,  Cable Trays, Raceways, Junction Boxes, Swtiches & Sockets, Light Fixtures, Earthing etc.
Divyasree Building, 3rd Floor,
Plot No.6, Hi-tech City, Sy.No.64(Part),  Madhapur Village, Serilingampalli Mandal,
Hyderabad-560 081.
Phase-4
Trion IT Park, Sy.No.35, Hissa Nos.9+10+11+12B at 7 Ahmednagar Road, Village Vadgaon Sheri, Pune-411 014
30,000 Sq.Ft. Area
CHENNAI Bangalore Pune JANUARY’ 2017
TO
MARCH’ 2017
74.00